TDS on contract payments in Nepal: when the 1.5% applies, on what amount and who pays it
When a public or private entity in Nepal pays a contractor under a contract, section 89 of the Income Tax Act 2058 requires it to withhold 1.5% as advance tax (TDS). It applies to the contract amount excluding VAT, only on payments above Rs 50,000, and the amount withheld is credited against the contractor's annual income tax.
- Published
- Checked against sources
- Author
- NepalConstruct team, Yoddha Lab

What is TDS?
TDS (tax deducted at source) is tax the payer holds back while paying and deposits with the Inland Revenue Department on the government's behalf. For a contractor it is not a final tax: at year end the TDS withheld is credited as advance tax against the income tax actually due.
What is the rate on contract payments?
| Type of payment | Rate |
|---|---|
| Contract or agreement payment to a resident, above Rs 50,000 | 1.5% |
| Contract payment to a non-resident | 5% |
| Service fee to a VAT-registered resident provider | 1.5% |
| Service fee to a PAN-only (not VAT-registered) provider | 15% |
The Rs 50,000 threshold is tested by adding together payments made under the same contract within the previous 10 days. Splitting a payment into small pieces does not avoid it.
On which amount: with or without VAT?
On the amount excluding VAT. If the contractor's tax invoice shows work of Rs 2,44,800 and VAT at 13% of Rs 31,824, TDS is 1.5% of Rs 2,44,800 = Rs 3,672, not 1.5% of Rs 2,76,624. VAT belongs to the government, not the contractor's income, so no income tax is withheld on it.
Example: one running bill
| Line | Amount (Rs.) |
|---|---|
| Adjusted value of work (before VAT) | 2,44,800.00 |
| VAT 13% | +31,824.00 |
| TDS 1.5% (on Rs 2,44,800) | -3,672.00 |
Rs 3,672 is deposited with the Inland Revenue Department against the contractor's PAN. The contractor claims it when filing the annual income tax return. The contractor should keep the TDS record (the certificate or the e-TDS entry) in its books.
Who deposits it, and when?
- The paying entity withholds and deposits it. The contractor does nothing, but must reconcile the record.
- Deposit deadline: within the prescribed days after the end of the month (current practice cites 25 days). Confirm with your accountant.
- If it is late or not withheld, the paying entity bears the tax plus interest.
In the contractor's books
- Record TDS withheld as advance tax receivable, not as an expense.
- Reconcile each bill's TDS, who withheld it and when, against the IRD record every quarter.
- When you pay a subcontractor you are the withholding party: deduct 1.5% and deposit it.
Frequently asked questions
Does the TDS come back?
Not directly, but it is credited against annual income tax. If the TDS exceeds the tax due, the excess can be claimed as a refund or carried forward.
Is TDS withheld when buying materials?
Plain supply of materials is not a contract payment, but where supply and installation sit in one agreement the whole payment is treated as a contract payment.
What if the subcontractor is PAN-only?
For construction contract payments the rate stays 1.5%; the 15% rate is for service fees to providers that are not VAT-registered. Construction contractors must register for VAT, so ask for a VAT invoice.
NepalConstruct's running bill computes TDS at 1.5% on the pre-VAT amount and posts it to an advance tax receivable account. The rate is a dated setting, so a rule change is one settings update.