Running bills & payment
Running bills must be paid within 30 days: what the rule says and what a properly submitted bill looks like
Under the Public Procurement Rules 2064, a running bill that the contractor submits properly, with the required documents, is to be checked, approved and paid by the public entity within 30 days. The clock starts on the date the complete submission is received, so an incomplete bill delays its own payment.
- Published
- Checked against sources
- Author
- NepalConstruct team, Yoddha Lab
The rule
The Rules tie the payment deadline to the contract conditions: the general conditions (GCC) and particular conditions (PCC) of the bidding document set the days, and PPMO's standard documents use 30. Some donor-funded contracts use 45 or 56 days, so read your own PCC.
A properly submitted bill: the checklist
- IPC submission letter with the bill number and period
- Measurement book page references, signed by both parties
- Measurement sheet and BOQ abstract (cumulative, previous, this bill)
- Price adjustment sheet and the index source (if applicable)
- Quality test reports and site photos
- VAT tax invoice matching the IPC amount exactly
- Previous payment details and the advance recovery statement
What if it is late?
- First send a written follow-up quoting the receipt date and the 30-day count.
- Check whether the contract's general conditions provide interest on late payment; if so, claim it.
- If the delay has stopped the work, claim an extension of time in writing and on time.
- Watch your receivables ageing (0-30, 31-60, 61-90 days) every week; it is the first warning of a cash-flow problem.
Frequently asked questions
Are the days working days or calendar days?
Usually calendar days. If the contract's PCC says otherwise, the PCC applies.
What if payment is late because the entity has no budget?
After the 2083 amendment a contract cannot be awarded without a confirmed budget and site. On older contracts budget shortfalls are a common cause of delay; written follow-ups and an interest claim rest on that record.
NepalConstruct records each running bill's measurement date and the payments received against it, ages receivables per contract in 0-30, 31-60, 61-90 and 90+ day buckets, and shows the total unpaid after 30 days on the dashboard.