Running bills & payment
How a running bill (IPC) is calculated in Nepal: from the measurement book to net payable, step by step
A running bill (IPC) starts from the quantities certified in the measurement book multiplied by the contract's BOQ rates. Price adjustment is added, VAT at 13% is added, and then TDS at 1.5%, retention at 5%, mobilisation advance recovery and liquidated damages are deducted in order to reach net payable. Get the order wrong and the amount is wrong.
- Published
- Checked against sources
- Author
- NepalConstruct team, Yoddha Lab

What is a running bill?
Large construction work runs for months, so the contractor is paid for work done at intervals rather than only at the end. That periodic bill is the running bill, running account (RA) bill or interim payment certificate (IPC). It becomes payable only after the public entity's engineer certifies it.
What is needed before the bill?
- Measurement book (MB): the quantity of work done on site, signed by both the contractor and the engineer.
- Measurement sheet and BOQ abstract: for each BOQ item, the cumulative quantity to date, the quantity already billed, and this bill's quantity.
- Test reports (concrete cubes, compaction), photos, and price adjustment indices where applicable.
- The contractor's VAT tax invoice and the IPC submission letter.
The order of deductions
| Step | Base |
|---|---|
| 1. Gross work = Σ (certified qty × BOQ rate), cumulative less previously billed | Measurement book |
| 2. ± Price adjustment (if the contract is eligible) | Gross work |
| 3. + VAT 13% | Adjusted work |
| 4. - TDS 1.5% | Adjusted work (excluding VAT) |
| 5. - Retention 5% | Adjusted work |
| 6. - Mobilisation advance recovery (pro rata) | Per the contract |
| 7. - Liquidated damages, if accrued | Per the contract |
| = Net payable |
Example: Rs 2,40,000 of work
Suppose this month's measurement book certifies Rs 2,40,000 of work, the contract is eligible for price adjustment (+2% this period), a mobilisation advance of 20% of the contract was taken and is being recovered in proportion to work done, and there is no delay.
| Line | Amount (Rs.) |
|---|---|
| Gross work done | 2,40,000.00 |
| Price adjustment +2% | +4,800.00 |
| VAT 13% (on Rs 2,44,800) | +31,824.00 |
| TDS 1.5% (on Rs 2,44,800) | -3,672.00 |
| Retention 5% (on Rs 2,44,800) | -12,240.00 |
| Mobilisation advance recovery 20% (on Rs 2,44,800) | -48,960.00 |
| Liquidated damages | -0.00 |
| Net payable | 2,11,752.00 |
The contractor's revenue is Rs 2,44,800; the cash that arrives is Rs 2,11,752. The difference is not lost: Rs 31,824 is VAT to remit (net of input VAT), Rs 3,672 is advance tax, Rs 12,240 sits in retention, and Rs 48,960 reduces the advance taken earlier.
Common mistakes
- Applying TDS to the VAT-inclusive amount: 1.5% × 2,76,624 is wrong.
- Counting quantities already billed: for each item, subtract what was billed before from the cumulative figure.
- Recovering the advance at a share other than the one written in the contract.
- Retyping BOQ rates by hand: the rate is the contract's record and must stay the same on every bill.
When is it paid?
Under the Public Procurement Rules, a properly submitted running bill with its supporting documents is to be approved and paid within 30 days. The clock does not start on an incomplete submission, so complete the list above before submitting.
Frequently asked questions
Are IPC and RA bill the same thing?
Yes. Interim payment certificate (IPC) and running account (RA) bill both refer to the periodic running bill. PPMO documents mostly use IPC.
What is different on the final bill?
The final bill reconciles all work to date against everything paid so far, recovers any remaining advance in full, and starts the retention release conditions.
Does every contract get price adjustment?
No. Typically only contracts longer than 12 months, using the formula and indices named in the contract document. Lump-sum contracts do not get it.
In NepalConstruct the running bill is built straight from the measurement book: no quantity is retyped, BOQ rates come from the contract, and VAT, TDS, retention, advance recovery and LD are computed in exactly this order and posted to an append-only double-entry ledger.