Retention money in Nepal's public works: how the 5% is held and when it comes back

Under Nepal's Public Procurement Rules 2064, a public entity holds 5% of every running bill as retention money. It is released in two halves: one when the defects liability period ends, and the other when the contractor shows proof of filing its tax return with the Inland Revenue Department.

Published
Checked against sources
Author
NepalConstruct team, Yoddha Lab
6 min read
An engineer reading plans on site
An engineer reading plans on site
Some figures in this guide can change with the latest amendment. Check the primary sources listed below and your own contract document before relying on them.

What is retention money?

Retention money is a part of the value of work done that the public entity keeps back from the contractor. It is not a penalty. It is security that defects found after completion will be corrected. The contractor does not receive it on the day the bill is passed, but it remains the contractor's money and comes back once the conditions are met.

How much is deducted?

In public works, 5% of each running bill (IPC) is deducted as retention. The rate is written in the particular conditions of the contract; PPMO's standard bidding documents use 5%. Private contracts can agree a different rate, but 5% is the common practice.

Retention is taken on the gross value of work, not on a VAT-reduced figure. VAT and TDS are computed on the gross first; retention and advance recovery come after.

When and how is it released?

  1. First half: after substantial completion and the end of the defects liability period (commonly 365 days), together with the release of the performance security.
  2. Second half: when the contractor submits proof that it has filed the income tax return for the relevant fiscal year with the Inland Revenue Department.

The second condition catches many contractors out: a late tax return holds half the retention for months. Filing the return for the year the project closes on time is the first step to getting the retention back.

Example: retention on one running bill

LineAmount (Rs.)
Gross work done (per the measurement book)2,40,000.00
Price adjustment (+2%)4,800.00
Adjusted value of work2,44,800.00
Retention 5%-12,240.00

Rs. 12,240 sits in the contractor's books as retention receivable. It is not lost revenue; it is money to be collected later. Across ten such bills, Rs. 1,22,400 is held, which is a large share of a small firm's cash flow.

How to account for it

  • When the bill is certified: the full value of work is revenue; the retention goes to a separate retention receivable account.
  • Compute TDS and VAT on the gross value, before the retention deduction.
  • Reduce the receivable as each half comes back; correct mistakes with a new entry, never by editing the old one.
  • Keep a register per project: how much from which bill, when the DLP ends, whether the tax return is filed.
The Public Procurement Rules 2064 have been amended many times (up to 2083). Check the rule numbers and percentages against your contract document and the current PPMO text.

Frequently asked questions

Does retention money earn interest?

Usually not. Standard public contract conditions do not provide interest on retention held by the public entity.

Can a bank guarantee replace retention?

Some contracts allow the contractor to replace the held retention with a bank guarantee of equal value after completion. It has to be written into the particular conditions of the contract.

Is retention the same as performance security?

No. Performance security is a bank guarantee given before signing (5% of the accepted bid). Retention is cash held from each bill. Both are released after the defects liability period.

How NepalConstruct handles this

In NepalConstruct the running bill deducts retention at the rate set on the contract and posts it to its own ledger account. The total held shows on each contract and carries into the next fiscal year at the year-end close.