Construction guides for Nepali contractors

Running bills, retention, TDS, bid capacity, rate analysis, SSF - a direct answer to each question, with a worked example and the primary source. Every guide is re-checked when a rule changes.

  1. Running bills & payment

    How a running bill (IPC) is calculated in Nepal: from the measurement book to net payable, step by step

    Measurement book, BOQ rates, price adjustment, VAT 13%, TDS 1.5%, retention 5%, advance recovery and LD: the full order of a PPMO-style running bill, with a Rs 2,40,000 worked example.

    8 min read
  2. Running bills & payment

    Retention money in Nepal's public works: how the 5% is held and when it comes back

    Public works contracts hold 5% of every running bill as retention and release it in two halves: one after the defects period, one on proof of the tax return. Rules, example and accounting.

    6 min read
  3. Tax

    TDS on contract payments in Nepal: when the 1.5% applies, on what amount and who pays it

    Under section 89 of the Income Tax Act 2058, contract payments above Rs 50,000 carry 1.5% TDS, computed on the amount excluding VAT. Non-residents pay 5%. Example and accounting.

    6 min read
  4. Contract terms

    Mobilisation advance in Nepal: up to 20%, against a bank guarantee, and how it is recovered from running bills

    After the 2083 amendment to the Public Procurement Act, mobilisation advance is capped at 20% of the contract amount (previously 30%), against an advance payment guarantee and a work schedule. Permitted uses, pro-rata recovery, example.

    6 min read
  5. Running bills & payment

    Running bills must be paid within 30 days: what the rule says and what a properly submitted bill looks like

    Under the Public Procurement Rules a properly submitted running bill with its documents is to be approved and paid within 30 days. When the clock starts, what to attach, and what to do when it is late.

    5 min read
  6. Running bills & payment

    The measurement book in Nepal: format, who signs, how corrections work and how it feeds the running bill

    The measurement book is a legal record: every entry maps to a BOQ item, both the contractor and the engineer sign, corrections never erase, and payment follows its quantities. Format and disputes.

    6 min read
  7. Estimation

    How to do rate analysis in Nepal: DUDBC/DoR norms × district rates, the 15% overhead and VAT

    Norms give the material, labour and equipment per unit of work; district rates give the prices. Their sum is the base rate, plus 15% contractor overhead, then VAT 13% at the abstract. RCC M20 example.

    8 min read
  8. Estimation

    BOQ format in Nepal: columns, sub-heads, the abstract of cost and the e-GP item order

    The six BOQ columns (item no., description, unit, quantity, rate, amount), grouping by sub-head, the abstract of cost with VAT 13% and contingencies, and the e-GP item order for bids. A five-item example.

    6 min read
  9. Tenders & e-GP

    Bid capacity in Nepal: the N × A − B formula, a worked example and the 5-contract cap

    In PPMO's standard documents, available bid capacity = N × A − B: A is the average construction turnover of the best 3 of the last 10 years, B the remaining value of ongoing contracts, N usually 5 or 7. A bid below the estimate's value is non-responsive.

    6 min read
  10. Tenders & e-GP

    Registering and bidding on e-GP (bolpatra.gov.np): documents, fees, security and the new 2083 deadlines

    Public tenders run only through e-GP. Registration documents, the document fee into the revenue account, uploading security, encrypted submission, and the post-2083 notice periods of 21 days (NCB) and 30 days (ICB).

    7 min read
  11. Tenders & e-GP

    Contractor licence classes A, B, C and D in Nepal: who issues them, what they need and when to renew

    Under the Construction Business Act 2055, Class A, B and C licences come from DUDBC and Class D from the local government. Engineer headcount, capital, one-fiscal-year validity and renewal within 3 months.

    6 min read
  12. Tenders & e-GP

    Performance security in Nepal: 5%, in what form, how long it must run and when it is released

    After the 2083 amendment, performance security is 5% of the accepted bid amount, as a bank guarantee before signing. Also bid security (2-3%), validity, forfeiture and release.

    6 min read
  13. Contract terms

    Price adjustment in Nepal's public works: the Pn formula, the indices, the 12-month condition and the 25% cap

    For contracts longer than 12 months, section 55 of the Public Procurement Act allows price adjustment: Pn = A + b·Ln/Lo + c·Mn/Mo + d·En/Eo, A = 0.15 fixed, indices from Nepal Rastra Bank/CBS, total adjustment capped at 25%. Example.

    7 min read
  14. Contract terms

    Variation orders in Nepal: the 5%, 10% and 15% approval tiers, rates for new items and how to document them

    After 2083, variation approval follows the cumulative percentage: up to 5%, up to 10%, up to 15% and above, each by a higher official. Work done without a written order is not paid.

    6 min read
  15. Contract terms

    Liquidated damages (LD) in Nepal: 0.05% per day, capped at 10%, and how an extension of time stops them

    For contractor-caused delay, 0.05% of the contract amount per day, up to 10%, is deducted from running bills. Paying LD does not excuse completion. Extension-of-time claims and an example.

    5 min read
  16. Tax

    CBMS e-invoicing in Nepal: which construction firms must run IRD-connected billing

    Per the IRD notice of 4 Baisakh 2083, businesses with annual turnover above Rs 20 crore must issue invoices through software connected to CBMS (lowered from 25 crore). What a contracting firm should do.

    5 min read
  17. Payroll & labour

    SSF for construction workers in Nepal: who pays what of the 31%, the basic-salary base and the deposit deadline

    The SSF contribution is 31% of basic salary: 11% from the worker (10% provident fund + 1% social security tax) and 20% from the employer (10% provident fund + 8.33% gratuity + 1.67%). Allowances are excluded. The four schemes, enrolment, example.

    7 min read
  18. Payroll & labour

    Nepal's minimum wage for 2082/83: Rs 19,550 a month, Rs 754 a day, and what it means on a construction site

    From 1 Shrawan 2082 the minimum remuneration is Rs 19,550 a month (basic 12,170 + dearness allowance 7,380), Rs 754 a day, Rs 101 an hour. Labour Act 2074 section 106. Overtime at 1.5×. Compared with site wages.

    5 min read
  19. Site operations

    Daily progress report (DPR) format: what a site engineer should record every day

    A DPR records date and weather, labour by naike, equipment hours, materials received and used, work done by BOQ item, hindrances and instructions, and photos. Format, responsibility and its link to the measurement book.

    6 min read
  20. Site operations

    Material reconciliation on site: how to find cement and rebar leakage before it eats the margin

    A monthly comparison of theoretical consumption (norms × work done) against actual consumption (store ledger), with a wastage allowance. A 100 m³ M20 cement example, BBS for rebar, and what to do when the variance shows.

    7 min read
  21. Software

    How to choose software for a contracting firm in Nepal: Excel, Tally and construction ERP compared, and 12 questions to ask

    Excel adds up but keeps no proof; Tally keeps the books but never sees the site. A construction ERP links the measurement book to the running bill. Nepali language, BS dates, the PPMO waterfall, SSF, offline: what to check.

    7 min read

These rules, applied by the system instead of by hand

The running-bill waterfall, retention, TDS and SSF are all computed in NepalConstruct from dated settings.