Running bills & payment

The measurement book in Nepal: format, who signs, how corrections work and how it feeds the running bill

The measurement book (MB) is the legal record of the quantity of work actually done on site, entered against BOQ items. Measurements are taken jointly by the contractor's representative and the public entity's engineer or sub-engineer, and both sign. Every amount on a running bill rests on a measurement book page reference; work not in the measurement book is not paid.

Published
Checked against sources
Author
NepalConstruct team, Yoddha Lab
6 min read
Tying reinforcement on site
Tying reinforcement on site

The format

ColumnWhat goes in it
Date (BS)The day the measurement was taken
BOQ item no. and descriptionExactly as in the contract BOQ
LocationGrid, floor, chainage, layer
No. × length × breadth × heightThe measured figures, with units
QuantityThe product, in the BOQ unit
RemarksDeductions, test references, instructions

Who signs?

  1. The engineer or sub-engineer who measured
  2. The contractor or authorised representative (accepted)
  3. The checking engineer (checked), usually the division or project chief
  4. The accounts section, when passing the bill against it

Rules for corrections

  • No erasing, no correction fluid, no torn pages. A mistake is struck through with a single line, the correct figure written beside it and initialled.
  • An entry already billed is never changed; the difference is settled by a further entry (negative or additional).
  • A computerised measurement book (CMB) follows the same principle: entries are never deleted; a correction is a new entry with an audit trail.

From the measurement book to the bill

Measurement book → measurement sheet (totals by item) → BOQ abstract (cumulative, previous, this bill) → running bill. Every bill abstract cites the measurement book page numbers so an auditor can trace any amount back to the site measurement.

The measurement book is the first evidence in any dispute. Record variations, instructions and hindrances the same day, in the measurement book or the site instruction book; what is written from memory later carries no weight.

Common disputes

  • Work done without measurement (buried foundations, for example): request the engineer in writing to measure, and keep dated photos before covering up.
  • Items not in the BOQ: even if entered in the MB, nothing is paid without a variation order.
  • Unit mismatch (m² or m³): the BOQ unit governs.

Frequently asked questions

Who keeps the measurement book?

The public entity. It is the entity's record; the contractor keeps certified copies.

Are photos and drone surveys accepted?

As supporting evidence. The basis of payment remains the signed measurement book entry.

How NepalConstruct handles this

NepalConstruct's measurement book is append-only: every entry links to a BOQ item, both parties certify it, a correction is a new entry, and the running bill is generated from it without retyping quantities.

Sources

  1. Public Procurement Rules 2064, consolidated English text (FAO)
  2. Department of Roads - publications (specifications and formats)
  3. Standard bidding documents for works - e-GP (bolpatra.gov.np)