Contract terms
Mobilisation advance in Nepal: up to 20%, against a bank guarantee, and how it is recovered from running bills
Mobilisation advance is money a public entity pays the contractor up front to start work. Under the Public Procurement Act as amended in 2083 it is capped at 20% of the contract amount, released only against a bank's advance payment guarantee and a schedule of the main activities, and recovered from each running bill in proportion to work done.
- Published
- Checked against sources
- Author
- NepalConstruct team, Yoddha Lab

How much, and on what conditions?
- Cap: up to 20% of the contract amount. Older bidding documents show 30%; the 2083 amendment set 20%.
- The maximum is not an entitlement; the entity may grant less where justified.
- Conditions: an advance payment bank guarantee equal to the advance, and a schedule of the main activities the advance will fund.
- Use: only for equipment, plant, materials, site preparation, labour camp and mobilisation expenses.
- Contracts with an estimate of Rs 20 million or more need a separate project bank account.
How is it recovered?
From each running bill in proportion to work done. The simple form: advance percentage × this bill's adjusted value of work. The contract document may set a different schedule (for example recovery starting after a set share of work), and the contract governs. Once the advance is fully recovered the guarantee is released; as it is recovered, the guarantee may be reduced accordingly.
Example
| Line | Amount (Rs.) |
|---|---|
| Contract amount | 1,00,00,000.00 |
| Mobilisation advance 20% | 20,00,000.00 |
| Adjusted work on IPC-01 | 2,44,800.00 |
| Recovery on IPC-01 (20%) | 48,960.00 |
| Advance outstanding | 19,51,040.00 |
When the contract completes, total work is Rs 1 crore and the 20% recoveries add up to exactly Rs 20 lakh. If the work ends below the contract amount (quantities fell), the remaining advance is recovered in full on the final bill or from the guarantee.
Cautions for the contractor
- The advance is a liability, not revenue; book it as advance repayable.
- Keep the guarantee valid beyond the contract period; renew it before expiry.
- Spending the advance on another project breaches the contract, and the 2083 Act spells out the permitted uses.
Frequently asked questions
Is interest charged on the advance?
In PPMO's standard documents the mobilisation advance is interest-free, but the contractor pays the bank's guarantee charges.
Can I decline the advance?
Yes. With your own cash you avoid the guarantee charges and the recovery bookkeeping, but for small firms the advance bridges the early cash gap.
In NepalConstruct the advance percentage and guarantee details are set on the contract; every running bill recovers automatically, the outstanding advance shows on the contract, and an alert fires 30 and 7 days before the guarantee expires.