Mobilisation advance in Nepal: up to 20%, against a bank guarantee, and how it is recovered from running bills

Mobilisation advance is money a public entity pays the contractor up front to start work. Under the Public Procurement Act as amended in 2083 it is capped at 20% of the contract amount, released only against a bank's advance payment guarantee and a schedule of the main activities, and recovered from each running bill in proportion to work done.

Published
Checked against sources
Author
NepalConstruct team, Yoddha Lab
6 min read
An excavator on a construction site
An excavator on a construction site
Some figures in this guide can change with the latest amendment. Check the primary sources listed below and your own contract document before relying on them.

How much, and on what conditions?

  • Cap: up to 20% of the contract amount. Older bidding documents show 30%; the 2083 amendment set 20%.
  • The maximum is not an entitlement; the entity may grant less where justified.
  • Conditions: an advance payment bank guarantee equal to the advance, and a schedule of the main activities the advance will fund.
  • Use: only for equipment, plant, materials, site preparation, labour camp and mobilisation expenses.
  • Contracts with an estimate of Rs 20 million or more need a separate project bank account.

How is it recovered?

From each running bill in proportion to work done. The simple form: advance percentage × this bill's adjusted value of work. The contract document may set a different schedule (for example recovery starting after a set share of work), and the contract governs. Once the advance is fully recovered the guarantee is released; as it is recovered, the guarantee may be reduced accordingly.

Example

LineAmount (Rs.)
Contract amount1,00,00,000.00
Mobilisation advance 20%20,00,000.00
Adjusted work on IPC-012,44,800.00
Recovery on IPC-01 (20%)48,960.00
Advance outstanding19,51,040.00

When the contract completes, total work is Rs 1 crore and the 20% recoveries add up to exactly Rs 20 lakh. If the work ends below the contract amount (quantities fell), the remaining advance is recovered in full on the final bill or from the guarantee.

Advance recovery does not reduce the tax base. VAT and TDS are computed on the full value of work; the recovery comes after, out of cash only.

Cautions for the contractor

  • The advance is a liability, not revenue; book it as advance repayable.
  • Keep the guarantee valid beyond the contract period; renew it before expiry.
  • Spending the advance on another project breaches the contract, and the 2083 Act spells out the permitted uses.
The 20% cap comes from the 2083 ordinance/amendment. Check the text in force and the percentage written in your own contract's PCC.

Frequently asked questions

Is interest charged on the advance?

In PPMO's standard documents the mobilisation advance is interest-free, but the contractor pays the bank's guarantee charges.

Can I decline the advance?

Yes. With your own cash you avoid the guarantee charges and the recovery bookkeeping, but for small firms the advance bridges the early cash gap.

How NepalConstruct handles this

In NepalConstruct the advance percentage and guarantee details are set on the contract; every running bill recovers automatically, the outstanding advance shows on the contract, and an alert fires 30 and 7 days before the guarantee expires.

Sources

  1. Public Procurement Act 2063 and Rules 2064 - PPMO
  2. Public Procurement Rules 2064, consolidated English text (FAO)
  3. Practical guide to the 2083 amendment (Engineering Sarathi, secondary source)
View all guides