BOQ format in Nepal: columns, sub-heads, the abstract of cost and the e-GP item order
A BOQ (bill of quantities) is the table listing every item of construction work with its description, unit, quantity, rate and amount, grouped under sub-heads (earthwork, concrete, reinforcement, brickwork, plaster, finishing, electrical, sanitary). Sub-head totals roll up into the abstract of cost, where VAT at 13% and contingencies are added. In a public tender the contractor prices the items in the e-GP order, and the measurement book and running bills are built on the same BOQ items.
- Published
- Checked against sources
- Author
- NepalConstruct team, Yoddha Lab
The six columns
| Column | Rule |
|---|---|
| Item no. | Numbered within the sub-head (1.1, 1.2 ... 2.1), matching the e-GP order |
| Description | The norm's item description word for word, with mix and thickness |
| Unit | m³, m², rm, kg, quintal, no.; never mixed within an item |
| Quantity | Taken off from drawings, to two decimals |
| Rate | From rate analysis (estimate) or filled by the bidder (tender), excluding VAT |
| Amount | Quantity × rate, to the paisa |
Example: five items
| Item | Unit | Qty | Rate (Rs.) | Amount (Rs.) |
|---|---|---|---|---|
| 1.1 Excavation in foundation (ordinary soil) | m³ | 120.00 | 285.00 | 34,200.00 |
| 2.1 PCC 1:3:6 in foundation | m³ | 12.50 | 11,450.00 | 1,43,125.00 |
| 2.2 RCC M20 in footing and columns | m³ | 38.00 | 15,778.92 | 5,99,598.96 |
| 3.1 Reinforcement Fe500, cut and tied | kg | 4,560.00 | 158.00 | 7,20,480.00 |
| 4.1 Brick masonry in 1:4 mortar | m³ | 64.00 | 18,900.00 | 12,09,600.00 |
The rates are illustrative; real rates come from rate analysis for your district and fiscal year. Note that reinforcement (3.1) is a separate item from concrete (2.2), and each item has its own unit.
The abstract of cost
- One line per sub-head total: earthwork, concrete, reinforcement, brickwork, ...
- Total (before VAT) → + VAT 13% → grand total
- Project-level contingencies: physical (often 10%) and price adjustment (often 10%), per the entity's practice
- An estimate BOQ carries rates; a tender BOQ leaves them blank for the bidder
Frequently asked questions
Are the BOQ and the cost estimate the same?
The BOQ is the table of quantities and rates; the cost estimate includes the BOQ, the rate analyses, the abstract and the drawing references.
How do I load an Excel BOQ into e-GP?
e-GP asks for rates in its own item order and format; export the BOQ in that order and fill only the rates. Descriptions and quantities remain the entity's.
In NepalConstruct the BOQ is a tree of sub-heads and items; rates come from norms × district rates, the abstract adds VAT and contingencies from settings, and the BOQ exports to Excel, or to CSV in the e-GP column order. The measurement book and running bills use the same items.