BOQ format in Nepal: columns, sub-heads, the abstract of cost and the e-GP item order

A BOQ (bill of quantities) is the table listing every item of construction work with its description, unit, quantity, rate and amount, grouped under sub-heads (earthwork, concrete, reinforcement, brickwork, plaster, finishing, electrical, sanitary). Sub-head totals roll up into the abstract of cost, where VAT at 13% and contingencies are added. In a public tender the contractor prices the items in the e-GP order, and the measurement book and running bills are built on the same BOQ items.

Published
Checked against sources
Author
NepalConstruct team, Yoddha Lab
6 min read

The six columns

ColumnRule
Item no.Numbered within the sub-head (1.1, 1.2 ... 2.1), matching the e-GP order
DescriptionThe norm's item description word for word, with mix and thickness
Unitm³, m², rm, kg, quintal, no.; never mixed within an item
QuantityTaken off from drawings, to two decimals
RateFrom rate analysis (estimate) or filled by the bidder (tender), excluding VAT
AmountQuantity × rate, to the paisa

Example: five items

ItemUnitQtyRate (Rs.)Amount (Rs.)
1.1 Excavation in foundation (ordinary soil)m³120.00285.0034,200.00
2.1 PCC 1:3:6 in foundationm³12.5011,450.001,43,125.00
2.2 RCC M20 in footing and columnsm³38.0015,778.925,99,598.96
3.1 Reinforcement Fe500, cut and tiedkg4,560.00158.007,20,480.00
4.1 Brick masonry in 1:4 mortarm³64.0018,900.0012,09,600.00

The rates are illustrative; real rates come from rate analysis for your district and fiscal year. Note that reinforcement (3.1) is a separate item from concrete (2.2), and each item has its own unit.

The abstract of cost

  • One line per sub-head total: earthwork, concrete, reinforcement, brickwork, ...
  • Total (before VAT) → + VAT 13% → grand total
  • Project-level contingencies: physical (often 10%) and price adjustment (often 10%), per the entity's practice
  • An estimate BOQ carries rates; a tender BOQ leaves them blank for the bidder
BOQ items are the basis of the measurement book, running bills and the material budget. The same work in two items or two units leads to double counting in measurement and billing later.

Frequently asked questions

Are the BOQ and the cost estimate the same?

The BOQ is the table of quantities and rates; the cost estimate includes the BOQ, the rate analyses, the abstract and the drawing references.

How do I load an Excel BOQ into e-GP?

e-GP asks for rates in its own item order and format; export the BOQ in that order and fill only the rates. Descriptions and quantities remain the entity's.

How NepalConstruct handles this

In NepalConstruct the BOQ is a tree of sub-heads and items; rates come from norms × district rates, the abstract adds VAT and contingencies from settings, and the BOQ exports to Excel, or to CSV in the e-GP column order. The measurement book and running bills use the same items.

Sources

  1. Standard bidding documents for works - e-GP (bolpatra.gov.np)
  2. Department of Roads - Norms for Rate Analysis and specifications
  3. Public Procurement Rules 2064, consolidated English text (FAO)