Estimation
How to do rate analysis in Nepal: DUDBC/DoR norms × district rates, the 15% overhead and VAT
Rate analysis in Nepal takes the quantity of materials, labour and equipment needed for one unit of work (say 1 m³ of concrete) from the norms (DUDBC or DoR) and prices them with the district rate. The sum of the three gets 15% contractor overhead, and VAT at 13% is added at the abstract of cost, not on the item rate.
- Published
- Checked against sources
- Author
- NepalConstruct team, Yoddha Lab

Three inputs: norms, district rates and policy
- Norms: how much cement, sand and aggregate, how many skilled and unskilled labour days, how many machine hours one unit of work takes. DUDBC norms for buildings; DoR's Norms for Rate Analysis of Road and Bridge Works 2075 for roads and bridges.
- District rate: the unit prices of materials, labour, equipment hire and carriage fixed at the start of each fiscal year by the district rate-fixation committee. Cement in Kathmandu and cement in Humla do not cost the same.
- Policy: contractor overhead at 15% (overhead and profit in one line), VAT at 13%, and contingencies at project level.
The formula
- Labour (a) = Σ labour days × district rate (by skill class)
- Materials (b) = Σ material quantity × district rate (including carriage lead)
- Equipment (c) = Σ machine hours × hire rate, with fuel and lubricants
- Base rate (d) = a + b + c
- Item rate = d × 1.15 (15% contractor overhead)
- At the abstract: Σ (quantity × item rate) + VAT 13% + contingencies
Example: RCC M20 (1:1.5:3), per m³, reinforcement excluded
The quantities follow a norm book and the prices one district's rate list; they are shown only to illustrate the method. Use your own district's rate book for the current fiscal year.
| Input | Quantity × rate | Rs. |
|---|---|---|
| Cement | 6.34 bags × 820 | 5,198.80 |
| Sand | 0.44 m³ × 2,600 | 1,144.00 |
| Aggregate | 0.88 m³ × 3,100 | 2,728.00 |
| Skilled labour | 1.0 day × 1,300 | 1,300.00 |
| Unskilled labour | 3.0 days × 900 | 2,700.00 |
| Mixer and vibrator | Hire share | 650.00 |
| Base rate (d) | 13,720.80 | |
| Contractor overhead 15% | 2,058.12 | |
| Item rate per m³ (before VAT) | 15,778.92 |
Where do district rates come from?
The District Administration Office and District Coordination Committee publish the district rate at the start of each fiscal year (many districts post the PDF on the office website). Because the rate book changes every year, record which fiscal year's rate an estimate used; an old estimate must keep its old rates.
Common mistakes
- Forgetting carriage: material district rates are often at source, not at site.
- Using last year's district rate.
- Putting reinforcement inside the concrete rate: it is a separate item (per kg or quintal).
- Doubling or reversing the 15% overhead and 13% VAT.
Frequently asked questions
What is the difference between DUDBC and DoR norms?
DUDBC norms are for building works, DoR norms for roads and bridges. Items, units and labour classes differ; the public entity names the applicable norms in the bidding document.
Does the 15% overhead include profit?
Yes. In government estimates overhead and profit are one 15% line; there is no separate profit line.
What if I bid far below the estimate?
A bid more than 30% below the estimate can be treated as abnormally low: you may be asked for a detailed rate analysis or disqualified. Your rate analysis must be able to justify your rates.
NepalConstruct keeps a norm library and a district rate table apart: norms × the (district, fiscal year) rate = item rate, with overhead and VAT as dated settings. The BOQ and abstract of cost follow from it and export to Excel, or to CSV in the e-GP column order.
Sources
- Department of Roads - publications (Norms for Rate Analysis of Road and Bridge Works 2075)
- Department of Urban Development and Building Construction (DUDBC)
- Suryabinayak Municipality rate analysis 2081/82 (worked municipal example)
- Nuwakot DAO district rate notices (example of an official district rate page)