Registering and bidding on e-GP (bolpatra.gov.np): documents, fees, security and the new 2083 deadlines

In Nepal every public tender above the quotation threshold is published and submitted only through PPMO's e-GP system at bolpatra.gov.np. A contractor registers once with its company, PAN/VAT, licence and tax clearance documents; for each tender it pays the document fee into the project's revenue account and uploads the voucher, attaches the scanned security and submits the encrypted bid before the deadline.

Published
Checked against sources
Author
NepalConstruct team, Yoddha Lab
7 min read
An engineer reviewing a plan
An engineer reviewing a plan
Some figures in this guide can change with the latest amendment. Check the primary sources listed below and your own contract document before relying on them.

Registration: once

  1. Create a bidder account at bolpatra.gov.np/egp; the company name must match the OCR registration exactly.
  2. Upload: OCR certificate, PAN/VAT certificate, contractor licence (current fiscal year), tax clearance certificate, letter of authority.
  3. Create users and roles; keep the login of the person who submits bids secure.
  4. Update the renewed licence and tax clearance every fiscal year; stale documents make a bid non-responsive.

For each tender

  1. Download the notice and bidding document (SBD) from e-GP; check the version and any addenda.
  2. Pay the document fee into the project's revenue (rajaswa) account at the bank and upload the voucher PDF. The fee is non-refundable.
  3. Arrange the bid security (bank guarantee, 2-3% of the cost estimate, valid 30 days beyond the bid validity) and upload the scanned copy.
  4. Fill the qualification forms (ELI, FIN-4 bid capacity, experience), the technical proposal, the work schedule and the priced BOQ.
  5. Submit well before the deadline; the system slows in the last hour. You may modify or withdraw before the deadline.

Opening and evaluation

Bids decrypt only after the opening time and only when two members of the opening committee log in together (dual control), then they are read out one by one. Qualification, technical and financial evaluation follow. A tie for the lowest evaluated bid is decided by lottery.

Deadlines and rules after 2083

ItemBeforeAfter 2083
NCB notice period30 days21 days
ICB notice period45 days30 days
Urgent procurement7 days3 days
Mobilisation advance30%20%
  • A bid more than 30% below the estimate is treated as abnormally low; rate analysis may be demanded or the bid rejected.
  • Domestic preference needs at least 30% Nepali value addition.
  • A contract cannot be awarded without a confirmed site and budget.
These periods and percentages come from the 2083 ordinance/amendment. The deadline printed in the tender notice itself is the one that counts.

Frequently asked questions

Do I need a digital signature for e-GP?

The system uses encrypted uploads and user authentication; check the current requirement in PPMO's user manual and the Electronic Procurement Guidelines 2080.

What if I find a mistake after submitting?

Before the deadline you can withdraw or modify and resubmit. After the deadline nothing can be corrected.

How NepalConstruct handles this

NepalConstruct's tender module records the tender's SBD version, the bid documents (including the document-fee voucher) and the submission time, tracks the bid security in the bank guarantee register, checks the six credentials and the 5-active-project cap, and exports the BOQ to Excel or to CSV in the e-GP column order.