Contractor licence classes A, B, C and D in Nepal: who issues them, what they need and when to renew

Contractor licences in Nepal are issued in four classes under the Construction Business Act 2055 and its Rules: Class A, B and C by the Department of Urban Development and Building Construction (DUDBC), Class D by the local government. The class depends on capital, experience, technical staff and equipment; a licence is valid for one fiscal year and must be renewed within 3 months of the year end.

Published
Checked against sources
Author
NepalConstruct team, Yoddha Lab
6 min read
An engineer reading a site plan
An engineer reading a site plan
Some figures in this guide can change with the latest amendment. Check the primary sources listed below and your own contract document before relying on them.

The four classes

ClassScopeIssued byMinimum technical staff
ALargest, national and internationalDUDBC5+ NEC engineers
BMedium to largeDUDBC3+ engineers
CMediumDUDBC2+ engineers/overseers
DLocal, small (entry level)Local government1+ licensed engineer
Capital and contract-value limits are printed differently by different sources (Class A Rs 2 crore or 3 crore, Class D anywhere from Rs 3 lakh to 50 lakh). This guide therefore gives no figure: confirm against the current Construction Business Rules, DUDBC or your municipality.

The registration chain

  1. Register the company or firm at the Office of the Company Registrar (OCR)
  2. PAN and VAT registration: construction contractors must register for VAT whatever their turnover
  3. Contractor licence: A/B/C from DUDBC, D from the local government, with proof of capital, engineers and equipment
  4. Register on e-GP (bolpatra.gov.np) for public tenders

The six credentials for a public bid

  • OCR registration certificate
  • PAN and VAT registration
  • A contractor licence of the right class, current for this fiscal year
  • Tax clearance certificate
  • The minimum number of NEC-registered engineers for the class
  • e-GP registration

Validity and renewal

A licence is valid for one fiscal year. It must be renewed within 3 months of the year end (by the end of Asoj) with the tax clearance certificate, financial statements and the fee. A firm with a lapsed licence cannot bid, and many firms lose tenders published in Shrawan and Bhadra for exactly this reason.

Frequently asked questions

How does a Class D firm move up to Class C?

Once the capital, completed-work experience, engineer count and equipment set in the Rules are met, the firm applies to DUDBC for Class C. Completion certificates for past work are the key documents.

How does class count in a joint venture?

The bidding document sets the class required of the lead partner and the minimum qualification of each partner. The 2083 amendment makes JV partners jointly and severally liable.

How NepalConstruct handles this

NepalConstruct stores the firm's licence class, number, issuing authority and fiscal-year expiry, alerts 60, 30 and 7 days before renewal, and shows red in the bid-eligibility check when the licence has lapsed.

Sources

  1. Construction Business Act 2055 (Nepali text, Kathmandu Metropolitan City law archive)
  2. Department of Urban Development and Building Construction (DUDBC)
  3. Nepal Law Commission (consolidated Acts and Rules)