Performance security in Nepal: 5%, in what form, how long it must run and when it is released

Performance security is the bank guarantee a contractor provides before signing the contract, securing completion of the work as agreed. Under the Public Procurement Act as amended in 2083 it is 5% of the accepted bid amount, must stay valid through the contract period and the defects liability period, and is released after that period together with the first half of retention.

Published
Checked against sources
Author
NepalConstruct team, Yoddha Lab
6 min read
Some figures in this guide can change with the latest amendment. Check the primary sources listed below and your own contract document before relying on them.

Two securities, two jobs

Bid securityPerformance security
WhenWith the bidBefore signing the contract
How much2-3% of the cost estimate (the document states the amount)5% of the accepted bid amount
ValidityAt least 30 days beyond the bid validity (often 90 days)Contract period plus the defects liability period, per the document
ReleaseTo unsuccessful bidders after evaluation; to the winner once performance security is inAfter the defects liability period

In what form?

  • An unconditional bank guarantee from a bank licensed in Nepal, in the exact PPMO format. A guarantee with altered wording can be rejected.
  • A foreign bank's guarantee only with a counter-guarantee from a Nepali bank.
  • In e-bidding the scanned security is uploaded on e-GP; the original is submitted within the stated time.

Abnormally low bids

For a bid well below the estimate (typically 15% or more below) the Rules allow additional performance security by formula. A bid more than 30% below the estimate can be treated as abnormally low, with a demand for rate analysis or rejection.

When is it forfeited?

  • If the selected bidder fails to provide performance security or sign within the 15-day window, the bid security is forfeited.
  • If the contractor abandons, breaches or fails to complete, the performance security is forfeited and blacklisting can follow.
  • When time is extended, the guarantee must be extended too; the entity may call a guarantee about to expire.
Keep the expiry of all three (bid security, performance security and advance guarantee) in one register, and ask the bank to renew 30 days before expiry.

Frequently asked questions

What does the bank charge for a performance guarantee?

It varies by bank: typically a small annual percentage plus margin (cash or collateral). The cost sits inside the overhead in your rate analysis.

Why both retention and performance security?

Performance security covers the whole contract; retention is cash from each bill that gives the entity an immediate fund for small defect repairs.

How NepalConstruct handles this

NepalConstruct's bank guarantee register holds the amount, bank, expiry and contract of each bid, performance and advance guarantee, with alerts 30 and 7 days before expiry.

Sources

  1. Public Procurement Act 2063 and Rules 2064 - PPMO
  2. Public Procurement Rules 2064, consolidated English text (FAO)
  3. Bid security and performance bond requirements in Nepal (Attorney Nepal, secondary)