Bid capacity in Nepal: the N × A − B formula, a worked example and the 5-contract cap
Bid capacity is the measure of how large a contract a contractor can take on, given its turnover and the work already in hand. PPMO's standard bidding documents define available bid capacity as N × A − B: A is the average annual construction turnover of the best 3 of the last 10 fiscal years, B is the remaining value of ongoing contracts, and N is the multiplier the document sets (usually 5 or 7). If capacity is below the cost estimate, the bid is non-responsive.
- Published
- Checked against sources
- Author
- NepalConstruct team, Yoddha Lab
The three numbers in the formula
- A, average annual construction turnover: the average of the best 3 of the last 10 fiscal years, supported by audited financial statements and tax clearance. Construction turnover only, not other businesses.
- B, work in hand: the value of work still to be done on ongoing contracts (contract amount less what has been billed), as of the bid date.
- N, the multiplier: 5 or 7 in PPMO documents; the entity may reduce it down to 1 for complex or large contracts. Read the FIN-4 form in your own bidding document.
Example
| Item | Amount (Rs. crore) |
|---|---|
| Best 3 years' turnover: 8.0, 6.5, 5.5 | Average A = 6.67 |
| N = 5 | N × A = 33.33 |
| Work in hand B | 12.00 |
| Available bid capacity | 21.33 |
This firm qualifies for contracts with a cost estimate up to Rs 21.33 crore. On a Rs 25 crore contract it fails on capacity even if turnover and experience pass. Two ways to raise capacity: finish old contracts faster to cut B, or bid in a joint venture.
The 5-contract cap
Since the 12th amendment to the Public Procurement Rules (2079), a firm may not hold more than 5 incomplete civil works contracts at once. A sixth needs one to finish first. This is a separate check from bid capacity; both must pass.
Before you bid
- Work out the remaining value of every ongoing contract as of today, from billed amounts, not estimates.
- Keep the 10 years of turnover figures reconciled with tax clearance and audit reports.
- In a JV, partners' capacities combine in the proportions the document sets, not in full.
Frequently asked questions
Does B include contracts that have not started?
Yes. A signed contract where work has not begun counts in full as work in hand.
Can subcontracted work be counted in turnover?
As the document allows; usually only construction turnover billed in the firm's own name counts.
NepalConstruct's tender module checks the 5-incomplete-contract cap and gives each bid a green, amber or red eligibility flag from the licence, PAN, VAT, tax clearance, e-GP registration and NEC engineers. Bid capacity from turnover history is not in the app yet; work it out with the formula above.