Bid capacity in Nepal: the N × A − B formula, a worked example and the 5-contract cap

Bid capacity is the measure of how large a contract a contractor can take on, given its turnover and the work already in hand. PPMO's standard bidding documents define available bid capacity as N × A − B: A is the average annual construction turnover of the best 3 of the last 10 fiscal years, B is the remaining value of ongoing contracts, and N is the multiplier the document sets (usually 5 or 7). If capacity is below the cost estimate, the bid is non-responsive.

Published
Checked against sources
Author
NepalConstruct team, Yoddha Lab
6 min read
Some figures in this guide can change with the latest amendment. Check the primary sources listed below and your own contract document before relying on them.

The three numbers in the formula

  • A, average annual construction turnover: the average of the best 3 of the last 10 fiscal years, supported by audited financial statements and tax clearance. Construction turnover only, not other businesses.
  • B, work in hand: the value of work still to be done on ongoing contracts (contract amount less what has been billed), as of the bid date.
  • N, the multiplier: 5 or 7 in PPMO documents; the entity may reduce it down to 1 for complex or large contracts. Read the FIN-4 form in your own bidding document.

Example

ItemAmount (Rs. crore)
Best 3 years' turnover: 8.0, 6.5, 5.5Average A = 6.67
N = 5N × A = 33.33
Work in hand B12.00
Available bid capacity21.33

This firm qualifies for contracts with a cost estimate up to Rs 21.33 crore. On a Rs 25 crore contract it fails on capacity even if turnover and experience pass. Two ways to raise capacity: finish old contracts faster to cut B, or bid in a joint venture.

The 5-contract cap

Since the 12th amendment to the Public Procurement Rules (2079), a firm may not hold more than 5 incomplete civil works contracts at once. A sixth needs one to finish first. This is a separate check from bid capacity; both must pass.

Check the multiplier, the experience threshold (completed work of 40% or 60% of the estimate) and the 5-contract count in the bidding document and the current Rules; these change with amendments.

Before you bid

  • Work out the remaining value of every ongoing contract as of today, from billed amounts, not estimates.
  • Keep the 10 years of turnover figures reconciled with tax clearance and audit reports.
  • In a JV, partners' capacities combine in the proportions the document sets, not in full.

Frequently asked questions

Does B include contracts that have not started?

Yes. A signed contract where work has not begun counts in full as work in hand.

Can subcontracted work be counted in turnover?

As the document allows; usually only construction turnover billed in the firm's own name counts.

How NepalConstruct handles this

NepalConstruct's tender module checks the 5-incomplete-contract cap and gives each bid a green, amber or red eligibility flag from the licence, PAN, VAT, tax clearance, e-GP registration and NEC engineers. Bid capacity from turnover history is not in the app yet; work it out with the formula above.