Daily progress report (DPR) format: what a site engineer should record every day

A daily progress report (DPR) is the site record a site engineer or overseer fills in every day: date and weather, workers present (by trade and naike), equipment hours, materials received and consumed, work done by BOQ item, hindrances and instructions, safety incidents and photos. It is not a payment document, but it is the first evidence behind the measurement book, extension-of-time claims and cost control.

Published
Checked against sources
Author
NepalConstruct team, Yoddha Lab
6 min read
Working on a construction site
Working on a construction site

The format: eight sections

SectionWhat to record
1. Date and weatherBS and AD date; weather (sunny, rain, hours lost)
2. LabourHeadcount by trade (mason, carpenter, helper), by naike, overtime
3. EquipmentRunning hours per machine, downtime, fuel
4. MaterialsReceived today (GRN no.), issued, balance in store
5. Work doneBOQ item, location, quantity (feeds the measurement book)
6. Hindrances and instructionsSite not available, drawings pending, entity instructions, who gave them
7. SafetyIncidents, PPE, toolbox talk
8. Photos and signaturesDated, located photos; signatures of the site engineer and the entity's representative

Why every day?

  • In an extension-of-time or LD dispute, only hindrances recorded on the day count as evidence.
  • Daily labour and material records expose ghost workers and material leakage the next day, not at month end.
  • Quantities carried into the measurement book must agree with the DPR; a mismatch triggers a re-measurement.
  • Financial progress (value of work ÷ contract amount) is not typed in; it is computed from DPR quantities × BOQ rates.
The DPR is evidence of work, not the basis of payment. Payment follows the signed measurement book. The DPR's job is to make the measurement book accurate and timely.

Common mistakes

  • Filling it in from memory at the week's end: dates and weather go wrong, hindrances get missed.
  • Writing only the total headcount; split it by trade and naike.
  • Photos without a date and location.
  • Reporting a hindrance verbally but never writing it down.

Frequently asked questions

Who signs the DPR?

The contractor's site engineer or overseer prepares it; a countersignature by the entity's site representative makes it stronger evidence.

How on a site with no internet?

On paper or in an app that works offline and syncs when the signal returns. What matters is filling it in the same day, with the date.

How NepalConstruct handles this

NepalConstruct's site app fills the DPR on the phone: work by BOQ item, labour by gang leader, machine hours, materials, hindrances and photos that cannot be swapped once sent. Unsaved edits stay on the phone, but sending needs a connection. Progress is computed from the DPR quantities.