Liquidated damages (LD) in Nepal: 0.05% per day, capped at 10%, and how an extension of time stops them
Liquidated damages (LD) are the pre-agreed amount a public entity deducts when the contractor causes delay. In Nepal's standard contract conditions it is 0.05% of the contract amount per day, up to a total of 10%, deducted from running bills. Paying LD does not release the contractor from completing the work.
- Published
- Checked against sources
- Author
- NepalConstruct team, Yoddha Lab
Rate and cap
| Item | Standard value |
|---|---|
| Daily rate | 0.05% of the contract amount per day |
| Maximum | 10% of the final contract price |
| Deducted from | Running bills, at the end of the deduction order |
| At the cap | Can become grounds for termination |
Example
Contract amount Rs 1 crore, 40 days past the completion date, no extension granted: LD = 1,00,00,000 × 0.0005 × 40 = Rs 2,00,000, deducted from the running bill for that period. At 200 days the formula gives Rs 10,00,000, which is the 10% cap; it goes no higher.
Which delays are excused?
- Caused by the entity: late site handover, late drawings or decisions, late payment.
- Extra work from variations, for which time must be extended.
- Force majeure as the contract defines it: floods, landslides, earthquake, strikes, epidemics.
What the contractor should do
- Log every hindrance in the daily progress report with its date; this is the evidence for an extension.
- When a variation is ordered, ask in writing for its effect on time as well.
- As the completion date approaches, compare the programme with actual progress and attribute the delay by party.
Frequently asked questions
Are LD and a penalty the same?
No. LD is a pre-agreed estimate of loss written into the contract; a penalty is a sanction set by law. The entity need not prove actual loss to deduct LD.
Is VAT charged on the LD deducted?
No. LD does not reduce the value of work; VAT and TDS are computed on the full value first and LD comes out of the cash afterwards.
In NepalConstruct the contract stores the LD rate and cap; once the completion date (including extensions) passes, the running bill computes LD automatically and stops at the 10% cap. Hindrances logged in the DPR stay on record, with dates and the party responsible, for any extension-of-time claim.