Contract terms

Liquidated damages (LD) in Nepal: 0.05% per day, capped at 10%, and how an extension of time stops them

Liquidated damages (LD) are the pre-agreed amount a public entity deducts when the contractor causes delay. In Nepal's standard contract conditions it is 0.05% of the contract amount per day, up to a total of 10%, deducted from running bills. Paying LD does not release the contractor from completing the work.

Published
Checked against sources
Author
NepalConstruct team, Yoddha Lab
5 min read
Some figures in this guide can change with the latest amendment. Check the primary sources listed below and your own contract document before relying on them.

Rate and cap

ItemStandard value
Daily rate0.05% of the contract amount per day
Maximum10% of the final contract price
Deducted fromRunning bills, at the end of the deduction order
At the capCan become grounds for termination

Example

Contract amount Rs 1 crore, 40 days past the completion date, no extension granted: LD = 1,00,00,000 × 0.0005 × 40 = Rs 2,00,000, deducted from the running bill for that period. At 200 days the formula gives Rs 10,00,000, which is the 10% cap; it goes no higher.

Which delays are excused?

  • Caused by the entity: late site handover, late drawings or decisions, late payment.
  • Extra work from variations, for which time must be extended.
  • Force majeure as the contract defines it: floods, landslides, earthquake, strikes, epidemics.
To be excused, an extension of time must be claimed in writing within the time the contract sets (often 28 days of becoming aware of the event). A late claim can leave LD in place even for a genuine cause.

What the contractor should do

  • Log every hindrance in the daily progress report with its date; this is the evidence for an extension.
  • When a variation is ordered, ask in writing for its effect on time as well.
  • As the completion date approaches, compare the programme with actual progress and attribute the delay by party.

Frequently asked questions

Are LD and a penalty the same?

No. LD is a pre-agreed estimate of loss written into the contract; a penalty is a sanction set by law. The entity need not prove actual loss to deduct LD.

Is VAT charged on the LD deducted?

No. LD does not reduce the value of work; VAT and TDS are computed on the full value first and LD comes out of the cash afterwards.

How NepalConstruct handles this

In NepalConstruct the contract stores the LD rate and cap; once the completion date (including extensions) passes, the running bill computes LD automatically and stops at the 10% cap. Hindrances logged in the DPR stay on record, with dates and the party responsible, for any extension-of-time claim.

Sources

  1. Public Procurement Rules 2064, consolidated English text (FAO)
  2. Standard bidding documents for works, general conditions - e-GP (bolpatra.gov.np)
  3. Practical guide to the 2083 amendment (Engineering Sarathi, secondary)
View all guides