Price adjustment in Nepal's public works: the Pn formula, the indices, the 12-month condition and the 25% cap
Price adjustment compensates for changes in the market prices of labour, materials and equipment over a long contract. Under section 55 of the Public Procurement Act 2063 and the Rules, contracts longer than 12 months (other than lump-sum) use the formula in the contract document, Pn = A + b·Ln/Lo + c·Mn/Mo + d·En/Eo, where A = 0.15 is the fixed part, b + c + d = 0.85, and the indices come from Nepal Rastra Bank/CBS. Total adjustment is capped at 25% of the initial contract amount.
- Published
- Checked against sources
- Author
- NepalConstruct team, Yoddha Lab

Which contracts qualify?
- Contracts longer than 12 months, unless the contract document says otherwise. (In practice many entities include it only beyond 20-24 months; read your PCC.)
- Not for lump-sum contracts.
- No adjustment for work done during delay caused by the contractor.
The formula
Pn = A + b × (Ln / Lo) + c × (Mn / Mo) + d × (En / Eo). A is the fixed, non-adjustable share (0.15); b, c and d are the labour, material and equipment weights set in the contract document (summing to 0.85); Lo, Mo and Eo are the indices at the base date (30 days before the bid submission deadline); Ln, Mn and En are the indices for the adjustment period. Value of work in the period × (Pn − 1) = the adjustment.
Where do the indices come from?
- Materials: Nepal Rastra Bank's national wholesale price index, construction materials
- Equipment: wholesale price index, transport vehicles and machinery
- Labour: a labour index or the change in minimum wage, as the document specifies
- When the current month's index is not yet published, the engineer may apply a provisional figure and correct it later.
Example
| Component | Weight | Index ratio | Product |
|---|---|---|---|
| Fixed A | 0.15 | - | 0.1500 |
| Labour b | 0.30 | 1.10 | 0.3300 |
| Materials c | 0.45 | 1.04 | 0.4680 |
| Equipment d | 0.10 | 1.02 | 0.1020 |
| Pn | 1.0500 |
With Rs 2,40,000 of work in the period, the adjustment is 2,40,000 × (1.05 − 1) = Rs 12,000 (+5%). It is added on the running bill's price adjustment line, and VAT, TDS and retention are then computed on the adjusted value.
Frequently asked questions
Is price adjustment a variation?
No. A variation changes quantities or scope; price adjustment adjusts the rate of the same work for market prices. Their approval and records differ.
Who sets b, c and d?
The public entity, in the contract data of the bidding document. Before bidding, the contractor should check whether those weights match its own cost structure.
In NepalConstruct each contract stores its price adjustment eligibility, the weights (A, b, c, d), the base date and a monthly index table; the running bill computes Pn automatically and enforces the 25% cap.