Contract terms

Price adjustment in Nepal's public works: the Pn formula, the indices, the 12-month condition and the 25% cap

Price adjustment compensates for changes in the market prices of labour, materials and equipment over a long contract. Under section 55 of the Public Procurement Act 2063 and the Rules, contracts longer than 12 months (other than lump-sum) use the formula in the contract document, Pn = A + b·Ln/Lo + c·Mn/Mo + d·En/Eo, where A = 0.15 is the fixed part, b + c + d = 0.85, and the indices come from Nepal Rastra Bank/CBS. Total adjustment is capped at 25% of the initial contract amount.

Published
Checked against sources
Author
NepalConstruct team, Yoddha Lab
7 min read
Construction machinery beside a road
Construction machinery beside a road
Some figures in this guide can change with the latest amendment. Check the primary sources listed below and your own contract document before relying on them.

Which contracts qualify?

  • Contracts longer than 12 months, unless the contract document says otherwise. (In practice many entities include it only beyond 20-24 months; read your PCC.)
  • Not for lump-sum contracts.
  • No adjustment for work done during delay caused by the contractor.

The formula

Pn = A + b × (Ln / Lo) + c × (Mn / Mo) + d × (En / Eo). A is the fixed, non-adjustable share (0.15); b, c and d are the labour, material and equipment weights set in the contract document (summing to 0.85); Lo, Mo and Eo are the indices at the base date (30 days before the bid submission deadline); Ln, Mn and En are the indices for the adjustment period. Value of work in the period × (Pn − 1) = the adjustment.

Where do the indices come from?

  • Materials: Nepal Rastra Bank's national wholesale price index, construction materials
  • Equipment: wholesale price index, transport vehicles and machinery
  • Labour: a labour index or the change in minimum wage, as the document specifies
  • When the current month's index is not yet published, the engineer may apply a provisional figure and correct it later.

Example

ComponentWeightIndex ratioProduct
Fixed A0.15-0.1500
Labour b0.301.100.3300
Materials c0.451.040.4680
Equipment d0.101.020.1020
Pn1.0500

With Rs 2,40,000 of work in the period, the adjustment is 2,40,000 × (1.05 − 1) = Rs 12,000 (+5%). It is added on the running bill's price adjustment line, and VAT, TDS and retention are then computed on the adjusted value.

When indices fall the adjustment can be negative. Total (positive) adjustment cannot exceed 25% of the initial contract amount. Check the 12-month condition and the 25% cap in the current Rules and your contract.

Frequently asked questions

Is price adjustment a variation?

No. A variation changes quantities or scope; price adjustment adjusts the rate of the same work for market prices. Their approval and records differ.

Who sets b, c and d?

The public entity, in the contract data of the bidding document. Before bidding, the contractor should check whether those weights match its own cost structure.

How NepalConstruct handles this

In NepalConstruct each contract stores its price adjustment eligibility, the weights (A, b, c, d), the base date and a monthly index table; the running bill computes Pn automatically and enforces the 25% cap.

Sources

  1. Public Procurement Act 2063 and Rules 2064 - PPMO
  2. Nepal Rastra Bank - statistics (wholesale price indices)
  3. Practices of price adjustment in selected construction projects (NepJOL, academic)
  4. Price adjustment in Nepal public procurement, 2026 guide (Niti Partners, secondary)
View all guides