Variation orders in Nepal: the 5%, 10% and 15% approval tiers, rates for new items and how to document them

A variation order is the public entity's written instruction changing a contract's quantities, scope or specification. Under section 54 of the Public Procurement Act and the 2083 amendment, approval is tiered by the cumulative variation percentage: up to 5%, up to 10%, up to 15%, and above 15% by the departmental chief. Extra work done without a written order is not paid.

Published
Checked against sources
Author
NepalConstruct team, Yoddha Lab
6 min read
Some figures in this guide can change with the latest amendment. Check the primary sources listed below and your own contract document before relying on them.

Approval tiers

Cumulative variationApproved by
Up to 5%Third-class gazetted officer (for example the project or division chief)
Up to 10%Second-class gazetted officer
Up to 15%First-class gazetted officer
Above 15%Departmental chief

The percentage is cumulative: a first variation of 4% and a second of 3% put the second one in the 7% tier. Which post holds which tier varies by entity; check your entity's delegation of authority.

Rates for new items

  1. If an existing BOQ item increases: the contract rate applies (the conditions may allow rate review for very large changes).
  2. If the item is not in the BOQ: a rate analysis from district rates and norms, adjusted by the contract's bid percentage above or below the estimate, approved by the entity.
  3. Working before the rate is approved is a risk; if urgent, obtain a written interim instruction.

The paper trail

  1. Site instruction or the contractor's proposal, with the reason (drawing discrepancy, ground conditions, entity request)
  2. Estimated quantity, rate and amount; effect on time
  3. Tiered approval; the variation order number
  4. Measurement in the MB citing the variation order; shown separately on the running bill
Do not work on a verbal assurance that approval will follow. Without it there is no payment, even if the work is in the measurement book.

Frequently asked questions

Does a variation also extend time?

Not by itself. If time is affected, ask for an extension in writing with the variation; otherwise LD remains a risk.

What about a variation that reduces quantities?

The contract amount falls; the conditions may allow an overhead claim for a large omission. The advance recovery schedule needs adjusting too.

How NepalConstruct handles this

In NepalConstruct a variation order computes the cumulative percentage and routes to the right approval tier, rate analysis for new items uses the same norms and district rates, and only approved variations reach the measurement book and the running bill.

Sources

  1. Public Procurement Act 2063, section 54 (variation) - PPMO
  2. Public Procurement Rules 2064, consolidated English text (FAO)
  3. Practical guide to the 2083 amendment (Engineering Sarathi, secondary)